The project involves supplying and installing a treatment unit designed to treat and neutralise wastewater from the mortuary. The process used will be chemical, based on the action of sodium hydroxide NaOH. It is imperative that all effluent from the autopsy room and, in principle, from all points where liquid discharges are likely to be contaminated, particularly with ATNC, be treated. These discharges are loaded with organic matter. In accordance with DGS/DH directive No. 138, CNTs will be inactivated in a treatment unit.
The process used will be chemical, based on the principle of the action of sodium hydroxide (NAOH). To ensure the neutralisation of the effluent and in particular the inactivation of ATNCs, in accordance with legislation, the contact time will be at least 1 hour at pH 12.2, then the chemically active effluent will be neutralised with acid to bring the pH down to between 6.5 and 7.5 so that it can be discharged into the urban network. All the effluent from the technical room will be stored in the treatment unit during the day so that it can be neutralised in the evening.
1) Storage and homogenisation tank: double-skinned HDPE (High Density Polyethylene) with a volume of 2,000 litres, equipped with : 1 manhole with cover, 1 effluent inlet port, 1 effluent outlet port, 1 ventilated port fitted with a carbon filter or to be connected to the building's secondary ventilation system. 3 level regulators, 1 agitator, 2 overhead lifting pumps, 1 stainless steel support for pumps and agitator.
2) Treatment tank: made of double-skinned HDPE with a volume of 2000 litres, equipped with : 1 manhole with cover, 1 effluent inlet port, 1 effluent outlet port, 1 ventilation port fitted with a carbon filter or to be connected to the building's secondary ventilation system, 3 level regulators, 1 agitator, 2 overhead lifting pumps, 1 stainless steel support for pumps and agitator, 2 connections for soda and acid injection, 1 connection for pH probe.
3) Neutralisation unit and acid-base pH regulator: 1 soda metering pump, 1 acid metering pump, 1 pH regulator, 1 pH probe, 1 electrical control cabinet for all equipment, 2 x 20-litre (27 kg) drums of acid, 2 x 20-litre (27 kg) drums of soda, 2 retention tanks.
4) Electrical control cabinet: Electrical control cabinet for the treatment unit with alarm reporting.
Option: Plug and Play installed in a 20-foot container.